S/N Project Title Project Description Contract Type (DED, ESA, EPC, FEED etc.) Client Period of Execution Project ManHours Project Status
1. Design for Installation of an XHP Separator at Alakiri Flow station Provision of a design solution for the routing of XHP gas wells from the Alakiri Gas plant to the Alakiri Flowstation for processing using an XHP separator to be relocated from CAWC3 Flowstation Detailed Engineering Design

Eroton Exploration & Production Company Ltd.

July. 2018 – Sept. 2018 1112 MHrs Completed
2. Provision of Consultancy and Project Management Services for Odidi-Warri Gas expansion project (OWEP) Provision of Project Coordination, Project Management, Monitoring, controlling, Verification and Validation of work executed by EPC contractor in Partnership with SYBAG limited. Consultancy/ Project Management  

 

Nigerian National Petroleum Corporation (NNPC)

May 2018- Dec. 2019 128,000 MHrs (Proposed) Ongoing
3. UNIUYO Engineering Complex Project Detailed Architectural and Engineering Design for Engineering complex

2-floor Engineering complex and 1 Stand Alone Workshop at the main campus of University of Uyo

Detailed Engineering Design

Mobil Producing Nigeria Unlimited

April. 2018 – July 2018 3900 MHrs Completed
4. Provision of Project Site management support for LACT Unit Installation Provision of Project management support for LACT Unit Installation Project Management

Eroton Exploration & Production Company Ltd.

Mar. 2018 – Jun. 2018 864 MHrs Completed
5. Integrated Facility Management Project–Phase 2 Facilities Baseline Data Development

SECTION 2

Data development and As-Built

Mobil Producing Nigeria Unlimited

 

Mar. 2018 – Nov. 2018 3510 MHrs Completed
6. Bonny River Terminal (BRT) Exposed Pipeline Remediation  

Hydrological Study for BRT Exposed Pipeline Remediation

 

Hydrological Studies

Mobil Producing Nigeria Unlimited

Mar. 2018 – Aug. 2018 1125 MHrs Completed
7. Cawthorne channel 1 to Cawthorne channel  2 Alternative Crude evacuation Pipeline Project Provision of Conceptual studies and Front End Engineering Design Conceptual Studies/    Front End Engineering Design

Eroton Exploration & Production Company Ltd.

Feb. 2018 – May. 2018 1328 MHrs Completed
8. Awoba-Krakama-Cawthorne channel 3 Alternative Crude evacuation Pipeline Project Provision of Conceptual studies and Front End Engineering Design Conceptual Studies/      Front End Engineering Design

Eroton Exploration & Production Company Ltd.

Jan. 2018 – May. 2018 1328 MHrs Completed
9. JV Structural Repair Project for Inim, Enang and Utue Platforms Brownfield Verification of Corroded structural members for Inim, Enang and Utue Platforms Brown Field verification and Production of Bill of materials for Construction

Mobil Producing Nigeria Unlimited

 

Dec. 2017 – April. 2018 1125 MHrs Completed
10. Alakiri Associated Gas solutions Conceptual Studies Provision of Conceptual Studies for Alakiri Associated Gas solutions Conceptual Studies

Eroton Exploration & Production Company Ltd.

 

Nov. 2017 – Dec. 2017 1328 MHrs Completed
11. Project management and Support Services for Alternative Crude Oil Export system Pipeline Project (ACOES) Provision of Project management for Alternative Crude Oil Export system Pipeline Project (ACOES) Project Management

Eroton Exploration & Production Company Ltd.

 

Oct. 2017 – Dec. 2017 264 MHrs Completed
12. 20 MW Natural Gas Cogeneration Power Plant Development at Amuwo Odofin, Lagos State, Nigeria Feasibility Studies for 20 mega watts natural gas Power Plant Feasibility Studies

BCH Sustainable Energy Partners

Sep. 2017 – Dec. 2017 174 MHrs Completed
13. LPG Extraction Plant Project (Pipeline Scope) Detailed Engineering Design for LPG Extraction plant targeted at extracting LPG, Propane & Condensate Products from rich associated gas

(EPC)

Detailed Engineering Design

Green Energy International Limited/Lekoil JV,

Lambda gas Dynamics Limited, PCC

Sep. 2017 – April. 2018

(Detailed Engineering)

2270 MHrs (Detailed Engineering) Completed
14. Engineering Design Support for Procurement and Installation of Gas Lift System Provision of Engineering Support for the procurement and Installation of gas Lift System for Alakiri and Cawthorne Channels Fields Follow-On Engineering

Eroton Exploration & Production Company Ltd.

Aug. 2017 – Dec. 2017 696 MHrs Completed
15. OML 99 Pig Receiver Drain Pan Overboard Scaffold Design Detailed Design for Overboard Scaffold Design for Pig Receiver Drain Pan on OML 99 Detailed Engineering Design

Total Exploration & Production Nigeria Limited

Aug. 2017 – Oct. 2017  

314 MHrs

 

Completed
16. AFD1 13-ESDV-340 Scaffold Design AFD1 13-ESDV-340 Scaffold Design Detailed Engineering Design

Total Exploration & Production Nigeria Limited

Aug. 2017 – Sep. 2017  

117 MHrs

 

Completed
17. 28-ES-3040 (A & B) Load bearing Scaffold Design Scaffold Design Load bearing for 28-ES-3040

(A & B)

Detailed Engineering Design

Total Exploration & Production Nigeria Limited

May. 2017 – June 2017  

234 MHrs

 

Completed
18. Engineering Design of OML 100 (FSO Unity) Emergency RADA Works Scaffold Design Engineering Design of OML 100 (FSO Unity) Emergency RADA Works Scaffold Design Detailed Engineering Design

Total Exploration & Production Nigeria Limited

Feb. 2017 –April. 2017  

187 MHrs

 

Completed
19. Engineering Design of OML 102 (OFON) boat surfer landing scaffold Detailed Engineering Design for of OML 102 (OFON) boat surfer landing scaffold Detailed Engineering Design

Total Exploration & Production Nigeria Limited

Jan. 2017 – Mar. 2017  

115 MHrs

 

Completed
20. Engineering Design for Conceptual study and FEED for Alakiri NAG condensate Storage Tank facility Provision of Feasibility study and FEED for Alakiri Non Associated Gas (NAG) condensate Storage Tank facility Feasibility Studies/     Front End Engineering Design

Eroton Exploration & Production Company Ltd.

Jan. 2017 – April. 2017 4847 MHrs Completed
21. Award of Contract for Consultancy Services for the Design of ADIM ABARIBA road, BIASE L.G.A in Cross River State Provision Consultancy Services for the Design of ADIM ABARIBA road, BIASE L.G.A in Cross River State Consultancy

Ministry Of Niger Delta Affairs

Jan. 2017 – Mar. 2017  1272 MHrs Completed
22. Award of Contract for Consultancy Services for the Design of Internal Road Network NKO, YAKURR L.G.A in Cross River State Provision Consultancy Services for the Design of Internal Road Network NKO, YAKURR L.G.A in Cross River State Consultancy

Ministry Of Niger Delta Affairs

Jan. 2017 – Mar. 2017 1331 MHrs Completed
23. Project Support Services Provision of Project Support Services Engineering Service Agreement

Shell Petroleum Development Company of Nigeria Limited

Jan 2017 – Jun. 2019 Contract Ceiling Applicable Projects are Ongoing on the ESA
24. Engineering Design Service Agreement for Various MPN Projects (ESA III) Provision of Engineering Services in performing Conceptual, Preliminary and Detailed Engineering, Integrity Management, Project Engineering Support, Procurement Technical Support Engineering Service Agreement

Mobil Producing Nigeria Unlimited

Nov 2016 – Nov 2019 Contract Ceiling Applicable Projects are Ongoing on ESA III
25. Engineering Design for Gas Lift for Alakri, Orubiri, Cawthorne Channel and Akaso fileds Provision of Detailed Engineering Design of Gas Lift for Alakri, Oribiri, Cawthorne Channel and Akaso fileds Detailed Engineering Design

Eroton Exploration & Production Company Ltd.

Oct 2016 – December 2016 1669 MHrs Completed
26. Engineering Design Service Agreement for OML 18 Provision of Engineering Design Service for various work packages on OML 18 for Three Years Engineering Service Agreement

Eroton Exploration & Production Company Ltd.

Jun 2016 – Jun 2019 Contract Ceiling Applicable Projects are Ongoing on the ESA
27. Escravos Export System Project Provision of Detailed Engineering Design of the Chevron Nigeria Limited Escravos export system on the Escravos Tank farm facility Detailed Engineering Design

Gramen Petroserve Nig Ltd./ Chevron Nigeria Limited (CNL)

May 2016 – April 2017 34,765

MHrs

Completed
28. Implementation of Corrosion Inhibitor Injection on HP Production Header on AMD2 (phase 2) Detailed Engineering Design for the Implementation of corrosion inhibitor injection on HP production header on Amenam Drilling platform 2. Detailed Engineering Design

Total Exploration & Production Nigeria Limited

 

 

Sep. 2015 – Dec 2015

1800 MHrs

Completed
29. Conversion of Well AMKP2-40 from water injector to oil producer Detailed engineering Design of AMKP2-40 as a water injector, connected to AMD 2 Water Injection manifold via 6” 1500# carbon steel flow line and replacement of Christmas tree with new oil production tree. Detailed Engineering Design

Total Exploration & Production Nigeria Limited

Sep. 2015 – Dec 2015

 868 MHrs

Completed
30. Supply of various

Engineering

Personnel for SPDC

ODIDI Project

Provision of Engineering

Personnel (1 Process, 1 Loss Prevention and Control, 1 Stress Analysis Engineers) for ODIDI project

Detailed Engineering Design

Desicon Engineering Limited/   Shell Petroleum Development Company of Nigeria Limited

May 2016 – May 2017

 8068 MHrs

Completed
31. Frame Agreement Contract For Engineering Studies And Design Engineering Services agreement for call-up contracts Frame Agreement

Total Upstream Nigeria Limited

Aug. 2015 – July 2016 Contract Ceiling Applicable Completed
32. Stress Analysis For Akpo Offloading Lines Detailed Engineering studies of Piping Stress Analysis and Report For Akpo Offloading Lines Detailed Engineering Design

Total Upstream Nigeria Limited

Jun. 2015 – July 2015  284 MHrs Completed
33. ANGO Pipelines Project DED of Two wellhead platform with two dual string hook up arms & equipment Detailed Engineering Design

CONOIL/MSI Africa Ltd.

/Greenstone Solution

Jan. 2015 – April 2015

3,419 MHrs

Completed
34. UFR Package of EGINA FPSO Detailed Engineering Design of UFR package in a joint team with Saipem. Detailed Engineering Design

SAIPEM Contracting Nig. Ltd/    Total Upstream Nigeria Limited

July 2013 – June 2015  

45,000 MHrs

(KOHASA scope)

Completed
35. OML 100 FSO UNITY OWT JASCON 1 Barge Stability Analysis Detailed Engineering of barge stability and analysis to validate the stability of the JASCON 1 barge for the transportation of the FSO OWT module. Detailed Engineering Design

Total Exploration & Production Nigeria Limited

 

May 2013 – June 2013  3200 MHrs Completed
36. MCC and Workshop Building , Meji Living Quarter Project Detailed Engineering Design for Motor control Center and Workshop building of the Meji Living Quarter platform Detailed Engineering Design

WECO Eng. & Const Co./  Chevron Nigeria Limited

May 2013 – Sept. 2013

 4,852 MHrs

Completed
37. EPC of Air Tugger Platform Detailed Engineering Design of Air Tugger platform Skid on BE802 main deck Detailed Engineering Design

TILONE Subsea/   Hallin Marine

April 2013 – May 2013

 522 MHrs

Completed
38. Engineering for RDS Skids on vessel BE 802 Detailed Engineering Design for RDS Skids on vessel BE 802 Detailed Engineering Design TILONE Subsea/ Hallin Marine Feb. 2013 – Mar. 2013

 302 MHrs

Completed
39. OML 100, FSO Unity Overboard Discharge Line Replacement with GRP Detailed Engineering for OML 100 FSO Unity overboard discharge line replacement from Carbon steel to Glass Reinforced Plastic Detailed Engineering Design

African Star Energy Services Ltd.

Feb. 2013 – Dec. 2013  1,875 MHrs Completed
40. OML58 Fresh Water Network Improvement (Phase 1) Detailed Engineering Design for OML 58, Obagi Flow Station Fresh Water network Improvement Detailed Engineering Design Vicbriggs Nigeria Ltd./ Total Exploration & Production Nigeria Limited

 

Jan. 2013 – Jun 2013  

2,125 M-Hrs

Completed
41. Mezzanine Deck Strength Assessment Services (vessel BE 802) Deatailed Engineering design of mezzanine deck amendment on Vessel BE 802 Detailed Engineering Design

TILONE Subsea/  Hallin Marine

 

Jan. 2013 – Feb. 2013

 175 MHrs

Completed
42. NOPL Project Control Building and Guard Houses. Detailed Engineering Design of Northern Option Pipeline Project Control Building and Guard Houses. Detailed Engineering Design

CICO Construction Limited / SAIPEM Contr. Nig. Ltd/            Total Exploration & Production Nigeria Limited

Jan. 2013 – Dec. 2013

 18,750 MHrs

Completed
43. 24” Gas Pipeline from Ogbainbiri to OB/OB (Replacement of damaged sections) Detailed Engineering Design for 24” Gas Pipeline from Ogbainbiri to OB/OB (Replacement of damaged sections) Detailed Engineering Design

TOPLINE Ltd./ DAEWOO Nig. Ltd./     Nigerian Agip Oil Company (NAOC)

Oct. 2012 – May 2013

 4,448 MHrs

Completed
44. OML 58: OLO Flare tip replacement Detailed Engineering Design of OLO Flare Tip replacement and Project Management. Detailed Engineering Design

Asbury Intl. Ltd/             Total Exploration & Production Nigeria Limited

Sep. 2012 – Nov 2012 2,240 MHrs Completed
45. Engineering Service Agreement FOR SSAGS PROJECT Provision of Engineering Personnel for  Detailed Engineering of Southern Swamp Associated Gas Solutions Project Engineering Service Agreement SAIPEM contr. Nig. Ltd/ Shell Petroleum Development Company Aug 2012 – June 2016 176,000 MHrs (KOHASA scope) Completed
46. OML 99 AMQ Helideck Upgrade Project Detailed Engineering for OML 99 AMQ Helideck Upgrade covering:        Preparation of Structural Engineering basis of design                            STAAD Pro model for analysis and Design verification and reports *IFC drawings Detailed Engineering Design

Asbury Intl. Ltd/            Total Exploration & Production Nigeria Ltd.

Feb. 2012 – May 2012 1,080 MHrs Completed
47. OSV LewekTuckan Upgrade Provision of Structural Engineering calculations and drawings for the installation of Reel Hub Drive and Overboarding chute Base. Detailed Engineering Design

Tilone Subsea/  TOTAL Upstream Nig. Ltd

 

May 2012 – July 2012 982 MHrs Completed
48. Flowlines Sectional Replacement at the East and West Corner of Ogbogu Flow Station Detailed Engineering Design of Flow Line Sectional Replacement at the East and West Corner of OGBOGU Flow Station Basic Engineering Design

Total Exploration & Production Nigeria Limited

Jan. 2012 – June 2012

 7,200 MHrs

Completed
49. OML99 Lightning Protection Upgrade on AMQ and AMP2. Basic Engineering Design Studies:

Provision of 2 point support of 2m (minimum)•Relocation of the existing ION Plasma generator on AMP2 electrical building to an elevation of at least 2m above the highest structure on AMQ2 above the radar located on AMQ telecom mast, and the provision of lightning protection for the radar.

Front End Engineering Design

Total Exploration & Production Nigeria Limited

Aug. 2011 – Sep. 2011 1,876 MHrs Completed
50. OML 58 Obagi F/S PECO filter installation for GPS and old NPS Basic Engineering Studies, for the installation of the PECO filter on each of the fuel gas lines to the five oil expedition pumps Basic Engineering Design 

Total Exploration & Production Nigeria Limited

May 2011 – Jul. 2011  

1,200 MHrs

Completed
51. OML58 Compact Prover Installation at Rumuekpe Metering Station- Basic Engineering. Basic Engineering Studies for 16” bi-directional Prover loop that was no-longer in operation and install a new Compact Prover with required appurtenances. Basic Engineering Design

Total Exploration & Production Nigeria Limited

May 2011 – Jul. 2011  

2,840 MHrs

 

Completed
52. OML100 Re-instate Accessibility to South-East Boat landing on Edikan Drilling Platform1-EDD1 Basic Engineering Design Studies :

Relocation of existing boat landing on the southern East of the jacket to the North East corner of the platform

Basic Engineering Design

Total Exploration & Production Nigeria Limited

April 2011 – June 2011 1520 MHrs Completed
53. Engineering for the Installation of Handrails, stoppers, and monorail with hoist at AMP1 Conversion of the North-West area of the weather deck on AMP1 to have additional storage space for chemicals and lubricants. The new storage area shall be provided with steel drum storage with a capacity for the storage of 60 drums when completed. Detailed Engineering Design

Total Exploration & Production Nigeria Limited

Jan. 2011 – Mar. 2011 1,850 MHrs Completed
54. Design of an Air Cooled Heat Exchanger Structural support in IMA Field, Langley. Design of an Air Cooled Heat Exchanger Structural support Detailed Engineering Design Chesroc Nigeria Limited Dec. 2010 – Feb. 2011 762 MHrs Completed
55. OML58 OB 090 Temporary Retention Pit Basic Engineering studies for Temporary Retention Pit used for the storage of drill cut with a 10,000m3 storage capacity. Basic Engineering Design

Total Exploration & Production Nigeria Limited

Nov. 2010 – Jan. 2011  960 MHrs Completed
56. Technical Assistance – Drafting Services in Support of TUPNI DW ECP Group Call-up Contract for Drafting and Technical Services to update COMPANY drawings according to mark-ups Engineering Service Agreement

Total Upstream Nigeria Limited

Oct. 2010 – Mar. 2011

 17,477 MHrs

Completed
57. Frame Agreement for Engineering Services

(OML 58 Upgrade Phase 1 Project)

Provision of Engineering Personnel for the detailed Engineering of Obite Treatment Centre, Obagi Flow Station, Ogbogu clusters. Engineering Service Agreement

SAIPEM Nontracting Nig. Ltd/    Total Exploration & Production Nigeria Limited

July 2009 – Dec 2015  

38,092.09 MHrs

(KOHASA personnel scope)

Completed

BACK